    YASCO bathroom now projected for early 2026 completion

    Published on

    spot_img

    Progress on the long-delayed bathroom facility at the YASCO Sports Complex remains slow, months after Cabinet announced in May that it would move to complete the structure.

    Government had projected completion by the end of 2025, but that target has now shifted to early 2026, with uncertainty still surrounding a firm deadline.

    During a visit to the country’s only track and field venue, Observer Media found the building partially advanced, with rafters installed and some plumbing completed. National coach and former athlete Teddy Daley said workers indicated the project could be finished by January.

    “They told us it should be completed by January, which would be ideal for our Christmas training camp since it includes showers,” Daley said. “The pace is slow, but we’re encouraged because we’re seeing more progress now than in the last decade.”

    The structure—started over 15 years ago under the former UPP administration—remained abandoned for years and overrun by bushes before work resumed. Sports Minister Daryll Matthew estimated in May that completing the project would cost around EC$350,000.

    National Housing is overseeing the work, though on-site sources said delays in materials continue to affect consistency.

    Latest articles

    Regional MSME Matching Grants Programme Extends Window 2 Application Deadline to July 24, 2026

    Micro, Small and Medium sized Enterprises operating as value chain groups are encouraged to...

    VIDEO: Bulk Waste Collection Continues in Cassada Gardens

    Bulk Waste Collection Continues in Cassada Gardens (Photo Credit- NSWMA)The National Solid Waste Management...

    Immigration Amnesty Programme Now Processing Around 40 Applications a Day

    Antigua and Barbuda’s immigration amnesty programme is now processing about 40 applications each day,...

    Twenty Young Footballers to Represent Antigua and Barbuda on Prestigious European Development Tour

    St. John’s, Antigua – Twenty of Antigua and Barbuda’s brightest young footballers are set...

    More like this

    Regional MSME Matching Grants Programme Extends Window 2 Application Deadline to July 24, 2026

    Micro, Small and Medium sized Enterprises operating as value chain groups are encouraged to...

    VIDEO: Bulk Waste Collection Continues in Cassada Gardens

    Bulk Waste Collection Continues in Cassada Gardens (Photo Credit- NSWMA)The National Solid Waste Management...

    Immigration Amnesty Programme Now Processing Around 40 Applications a Day

    Antigua and Barbuda’s immigration amnesty programme is now processing about 40 applications each day,...